Phase 1 Corral Hollow Road & Valpico Road Temporary Traffic Signal Installation (Under Construction)

Proposed Timeline

Phase 1

2022

2023

February 2022 – March 2022
Design
April 2022 – June 2022
Construction Bid Period
June 2022 – November 2022
Construction
September 2023 - October 2023
Modify Configuration
November 2022 - August 2023
Traffic Study